UTILITIES
|
Guardrail to Protect Above-Ground Sewer Trunk Lines on Palos Verdes Drive South |
LACSD |
- Construction is imminent and should take about one week. LACSD will closely coordinate with the City due to adjacent projects.
|
Feb 2024 |
Underground Sewer Lines in Seaview Neighborhood |
LACPW: Mains
Homeowners: Laterals |
- Completed the last repair two weeks ago. There are currently no other issues. All lines are functioning.
- The City requested regular CCTV inspections. The City and LACPW will discuss further, including an inspection schedule.
- SMD crews continue to monitor the condition within the slide area on Dauntless and Exultant, Admirable, and PVDS.
|
Ongoing |
Sewer Lines in Portuguese Bend Community |
City |
- CCTV inspection completed, deviations found; Ramzi and Juan have the info.
- Repairs are being made today on Lower Cinnamon from Thyme up to the gravity line.
|
Ongoing |
Leaning SCE Power Poles Repairs |
Southern California Edison (SCE) |
- No updates from SCE.
- Frontier completed work above Dauntless. Still coordinating access to two residences.
- Gordon Leon reported one location where the electrical line is only 9 feet above ground.
- Cox needs to check their network on the poles above Dauntless. Ramzi Awwad will follow up with Cox.
|
Ongoing |
Gas Lines in Portuguese Bend Community |
SoCal Gas |
- Pushing back the schedule to 4/8/2024 for sites 2 and 3 due to coordinating the easement needed.
|
TBD |
Water Mains in Seaview Neighborhood |
Cal Water |
- Inspection crews noticed an above-ground main that shifted/dropped. Crews shored up the main.
|
TBD |
Water Mains in Portuguese Bend Community Association |
Cal Water |
- Small project to install a portable booster connection to minimum service disruptions during construction.
|
TBD |
Vanderlip Trail Water Mains |
Cal Water |
- There was a main break reported today. The main was pulled apart at the collar. It was also repaired today.
|
TBD |
Vanderlip Drive Water Mains |
Cal Water |
|
TBD |
Portuguese Bend Club |
Cal Water |
- Cal Water staff met on site with Eric Johnson and others to discuss the project and logistics.
- A geotechnical investigation needs to be conducted to assess feasibility.
|
TBD |
PVDS at Wayfarers Chapel |
Cal Water |
- Cal Water will coordinate with the City on PVDS repairs so that Cal Water work does not interfere with other City construction projects along PVDS at Wayfarers Chapel.
|
TBD |
CITY
|
Portuguese Bend Landslide EIR and Final Engineering |
City |
- Work continues to finalize the EIR. Addressing individual comments.
- Emergency hydraugers design continues. E1 launch area is the pull out along PVDS. E1 will be directionally drilled. E1 is the area with the most artesian pressure and will provide the most benefits. E2 launch site is at the end of Narcissa being accessed from Peppertree; there is a dirt access road (discharge line for well #19 goes across this road). E2 will be horizontally drilled. Inclinometers will be installed in the test bore holes. See the graphic/map below the table.
- Final design continues.
|
October 2024 |
PVDS at Peppertree Drainage |
City |
- No changes. Waiting for next steps with FEMA.
|
TBD |
GPS Surveying of Landslide Movement |
City |
- Next survey is mid-April 2024 and the City is adding several more monitoring points.
|
Ongoing |
PVDS Roadway Repairs |
City |
- Interim repairs at the ski jump were completed.
- The City is continuing design efforts for a more substantial repair at the ski jump. The City is working through details and is looking to minimize construction closure(s). PBCA is concerned with drivers using the neighborhood as a detour. The City will work with PBCA on the details and signage. The City will also coordinate with first responders. Construction may wait until school is out for summer break.
- New signage installation will start on 4/8/2024 (was delayed due to rain).
|
Ongoing |
Crack-Filling in Seaview Neighborhood |
City (RPV) |
- Crack filling will continue as needed.
- The City will investigate drainage.
- The City is aware of the new crack forming on Exultant. It will be filled before the next expected rain.
|
Ongoing |
COMMUNITY ASSOCIATIONS AND LANDSLIDE ABATEMENT DISTRICTS
|
Road Repairs in the Portuguese Bend Community |
Portuguese Bend Community Association |
- At Lower Cinnmon (1 to 3 Cinnamon), repairs will be conducted 4/8/2024 through 4/9/2024.
- At Lower Narcissa, asphalt patching at the gate with CMB will be conducted on 4/9/2024.
- CMB filling will be conducted at Narcissa curve.
- At the road above Wayfarers Chapel, the asphalt will be removed and replace with CMB on 4/10/2024. Will re-asphalt before next winter rains.
- At Sweet Bay, repairs will be conducted on 4/11/2024.
- PBCA will coordinate the work listed above with the utilities because utility work will also be done during this period.
- Looking into height restriction signage and placement.
- PBCA is changing the Narcissa gate code for residents only. The goal is to lessen truck traffic. All loaded trucks need to use the Peppertree entrance.
|
Ongoing |
KCLAD Dewatering Wells |
KCLAD |
- The last two weekends had excessive rains. This caused an impact on the club where mud and sand entered the pumping area.
- Three of 4 pumps are working.
- Water table has receded a bit.
- Pump #1 at well #3 went down on Friday. KCLAD isolated the issue to the control box. KCLAD is trying to get a repair person there quickly.
|
Ongoing |
Klondike Canyon Fissures |
KCLAD & City |
- The tarps and sandbags need to be checked before the expected rains this weekend.
- The City maintenance crews check them on a schedule and before rains.
|
Ongoing |
Klondike Canyon Culvert and Pipe |
KCLAD & City |
- Funding requests are still being submitted to funding agencies. Some have been rejected.
- A committee is sending letters to agencies.
|
Ongoing |
Lower Seaview/ PVDS at Klondike Canyon Drainage |
KCLAD & City |
- Surface drainage has become a problem with the rising beach. That area of the beach continues to rise.
|
TBD |
ACLAD Dewatering Wells |
ACLAD |
- Normal well maintenance continues.
|
Ongoing |
Dewatering Wells South of PVDS |
ACLAD & City |
- At wells #9 and #19, the power pole is in and is wired from the pole to the well. Well #9 has a pump in well with a generator and it works. Well #19 pump will be installed 4/4/2024. At well #19, there was a hole discovered in the screen and it is not as deep as previously thought.
|
Feb 2024 |
General Maintenance |
ACLAD |
|
Ongoing |
Kelvin Canyon Spring |
ACLAD & City |
- Ordered 4” drainpipe so they can drain the water from Indian Spring.
|
TBD |
Altamira Canyon Lining |
ACLAD, RPV, and LACPW |
- Clearing of Altamira canyon today.
- Gordon Leon found water coming down the canyon and then going into ground.
- Two of three grant applications have been submitted.
|
TBD |